Frac Plugging Op Underway at Samson's Earl Well
Thursday, April 28, 2011
Samson O&G Ltd.
Samson O&G advised that operations on the Earl #1-13H to drill out the 19 frac plugs is underway. This operation, which commenced last week, has been hampered by difficult weather conditions, by the stand down of the rig crew for Easter and by equipment breakdowns. The operation is now back on track, however and the first of the nineteen plugs had been drilled as of 0700 hours CST this morning.
Prior to the first plug being drilled, the oil rate from the well for the previous 24 hours was 292 BOPD. After the first plug was drilled, the rate was measured at 960 BOPD over a two hour period, prior to commencing the drill out of the second plug. Neither of these rates is considered to be a conclusive indicator of the well's initial production performance, as this can only be determined once all of the plugs have been removed. Samson is, however, encouraged by the marked increase in the oil rate from just one of the nineteen plugs being removed.
Oil and Gas International News Post Oil and Gas Energy Industry Business Markets News Update
Crude Oil Price by oil-price.net
Oil and Gas Energy News Update
Showing posts with label Samsons. Show all posts
Showing posts with label Samsons. Show all posts
Thursday, April 28, 2011
Tuesday, April 5, 2011
Frac Stimulation Ops Begin at Samson's Earl Well
Frac Stimulation Ops Begin at Samson's Earl Well
Tuesday, April 05, 2011
Tuesday, April 05, 2011
Samson O&G Ltd.
Samson O&G advised that fracture stimulation operations on the Earl #1-13H started on Saturday, April 2nd. Pumping operations are currently expected to be completed by April 7th and flow back operations will commence shortly thereafter.
While there have been some weather-induced delays, as of Monday 0600 hours April 4th, Stages 1 to 4 had been pumped, and Stage 5 was about to be pumped.
The stimulation plan involves 20 stages, which will place a total of 2.7 million pounds of proppant in the 5,700 foot horizontal section.
While there have been some weather-induced delays, as of Monday 0600 hours April 4th, Stages 1 to 4 had been pumped, and Stage 5 was about to be pumped.
The stimulation plan involves 20 stages, which will place a total of 2.7 million pounds of proppant in the 5,700 foot horizontal section.