Wednesday, August 3, 2011

Statoil Wraps Up First Phase at Gudrun Platform

- Statoil Wraps Up First Phase at Gudrun Platform

Wednesday, August 03, 2011
Statoil

The steel support structure for the Gudrun platform is now in place on the North Sea field, completing the first phase of the extensive installation work being carried out there.

"The entire operation has been carried out according to plan and in a secure manner," reported Anders Opedal, senior vice president for projects in Statoil's Technology, Projects and Drilling business area.

"We've passed an important milestone for coming on stream at the right time and to budget. With the jacket solidly positioned on the seabed, we'll be able to start drilling in the fourth quarter as planned."

Installation of the steel structure began on July 24, and the job of attaching it to the seabed was completed on August 2 when the last of 12 60-meter piles was driven home.

Saipem 7000, the world's second-largest crane vessel, has been used to carry out the installation work on Gudrun.

Weighing some 7,000 tonnes all told, the traditional jacket comprises two main structures of almost 2,300 tonnes each, tied together by six horizontal frames and various bracings.

Important contribution

"Gudrun is the first of a number of new installations in an area of the Norwegian North Sea which is both highly interesting and mature," observes Ivar Aasheim, senior vice president for field development in the Development and Production Norway business area.

"By exploiting existing infrastructure for processing and transport, we're ensuring production from new fields. Gudrun will also make an important contribution to maintaining high production levels going forward."

The next development milestone is the start of pre-drilling production wells on the field. These will be tied back to the platform for partial processing and oil and gas export.

Final processing of Gudrun's output will take place on Sleipner A, with the gas piped to the adjacent Sleipner T platform for carbon dioxide removal.

In addition, electricity to operate the Gudrun installation once it comes on stream in two years' time will be supplied from Sleipner A.

Gudrun ranks as one of Statoil's largest development projects on the Norwegian continental shelf, and contains some 127 million barrels of oil equivalent.

Oil & Gas Post

Promote Your Page Too
LINK

Thursday, June 23, 2011

Statoil: Gudrun Proj. On Schedule

- Statoil: Gudrun Proj. On Schedule

Thursday, June 23, 2011
Statoil

The steel jacket for the Gudrun field operated by Statoil in the Norwegian North Sea was named on June 22 at Kværner Verdal in mid-Norway.

The champagne bottle splashed "holy" water from the Ol spring over bright yellow steel when it was broken during the traditional naming ceremony at the yard.

Performing this deed was Jørgen Suul, a Kværner Verdal employee who had proposed the name Idun for the structure.

"Today's ceremony marks an important milestone on the way to starting production in 2014," said Anders Opedal, senior vice president for projects in Statoil.

Discovered in 1974, Gudrun has had to wait for 40 years before being converted from find to producing field.

"We've take a long time to understand this reservoir, which is complex and demanding," explained Jan Einar Malmin, Statoil's venture manager for the field.

With high pressure and temperature, the formation still hides secrets. Its name can actually mean "hidden knowledge" in Old Norse.

The plan for development and operation (PDO) estimates recoverable reserves at 132 million barrels of oil equivalent – but this figure is by no means set in stone.

Systematic work will be needed to reach it, said Malmin. "The gap between the highest and lowest forecast is unusually wide in Gudrun's case."

New technology, greater knowledge of the area and re-use of existing offshore infrastructure have finally made it possible for Statoil and partner GDF Suez to develop the field.

"This is an important milestone in the project for meeting the target of a production start-up on 2014," said Carl Otto Hauge, head of non-operated licenses at GDF Suez.

"Gudrun is a very important project for us, and underscores our presence on as well as our long-term commitment to and investment on the Norwegian continental shelf."

To maximize Gudrun's value, the project team is pursuing two main strategies – tackling sub-surface uncertainty and securing future production, and reducing development costs.

"Cost efficiency and secure development are goals for all our whole portfolio," said Opedal. "With our strong focus on costs and time, good planning and ownership of these plans are crucial."

And Gudrun is on schedule, he noted. "We'd planned to name the jacket at the end of June. That's now been done, and the structure will soon be towed out to the field."