Wednesday, May 25, 2011

Otto to Commence Abandonment Ops at Duhat Sidetrack

- Otto to Commence Abandonment Ops at Duhat Sidetrack

Wednesday, May 25, 2011
Otto Energy Ltd.

Otto provided the following update on the progress of the Duhat-1A sidetrack well, located in the Philippines.

Since the last update, the well was drilled to 321 m TVD (True Vertical Depth) in the 12 ¼” section before becoming stuck, again due to unstable hole conditions (similar to those experienced in the Duhat-1 nearby well).

The well was subsequently plugged back to 200 m TVD and abandonment operations have commenced.

Information obtained during drilling from both Duhat-1 and the Duhat-1A sidetrack are very encouraging. In both wells, high general background gas levels have been observed during drilling, consistent with the presence of an oil generative area. These high gas levels, in formations of relatively weak rock strength coupled with unexpected shallow overpressure in the Miocene Tagnocot interval require further study prior to the recommencement of exploration in the block.

Drilling further ahead in Duhat-1A is now considered to be imprudent on safety grounds and abandonment is now in progress.
Otto Energy Ltd and its partners in SC-51 are excited by the geotechnical results of this initial drilling campaign and further work will be programmed once the data from recent operations have been fully analyzed.

Oil & Gas Post

Promote Your Page Too

Monday, May 16, 2011

Otto Notes Drilling Ops at Duhat Well

- Otto Notes Drilling Ops at Duhat Well

Monday, May 16, 2011
Otto Energy Ltd.

Otto provided the following update on the progress of the Duhat-1 well. Since the last update, the well was drilled to 325m TVD (True Vertical Depth) in the 12 ¼" section before becoming stuck due to unstable hole conditions (similar to those experienced at this depth in the nearest offset well).

The well was subsequently plugged back to 224 meters TVD and successfully sidetracked. The well is currently drilling ahead at 295 meters TVD.

Geological prognosis is unchanged and rig performance is satisfactory to execute the work program.

Oil & Gas Post

Promote Your Page Too

Thursday, April 28, 2011

Otto Drills Ahead at Duhat Well

Otto Drills Ahead at Duhat Well

Otto provided the following update on the progress of the Duhat-1 well that was spudded on April 19, 2011. The well has been drilled to 205m TVD (True Vertical Depth) and 13 3/8" casing has been set and cemented. Current operations are pressure testing the Blow Out Preventer and installing flare lines prior to drilling ahead in 12 ¼" hole.

Performance of both the rig and mud system has been satisfactory with the well being on track to reach TD (Total Depth) as programmed.