Friday, June 10, 2011

Statoil Gets OK for Development of Visund South Fast Track

- Statoil Gets OK for Development of Visund South Fast Track

Friday, June 10, 2011
Statoil

The Norwegian Ministry of Petroleum and Energy has approved the plan for development and operation for Visund South. Production is planned to start up in the third quarter of 2012, and a subsea template is already on its way out to the field.

Visund South, which is located 10 kilometers from both the Gullfaks C and Visund A platforms in the North Sea, is a subsea development consisting of a template with four slots, from which three wells will be drilled and tied to Gullfaks C for processing.

"With the approval of the ministry, this first project in a series of fast-track developments is well underway, just four months after the PDO was submitted in January. This also means we're one step closer to our goal of halving the time taken from discovery to production," said Statoil senior vice president of Norwegian continental shelf field development Ivar Aasheim.

In the course of June everything will set for the installation of the seabed template, so that the project can commence drilling in August.

The template is the first one built that has its basis in a standard catalogue for subsea equipment, which was compiled in collaboration with the suppler industry. This catalogue will be used for the forthcoming fast-track developments.

Visund South will be installed on the field in conjunction with the Marulk development, which Statoil is carrying out now on behalf of operator Eni.