The Skarv FPSO stay at Kvaerner Stord yard has been extended to mid July 2011.
This is due to more work than anticipated with the pressure testing of the process plant, completion and hand over of equipment and systems. This work is best completed while the vessel is at the yard.
Our priority is safe, compliant and efficient start up of production which is now deferred from 3Q to 4Q 2011. In the period between tow out and start up the vessel will be installed and connected to the subsea infrastructure including pull in of risers, completion of commissioning and full system integration tests and start up preparations.